Live Engineering Transparency

Real-Time Build Transparency. Verified Milestone by Milestone.

Follow the live, physical construction progress of our active off-plan developments at Bahari Starlet and Bahari Central, or review our successfully delivered masterworks at Bahari Homes.

Our Uncompromising Commitment to Complete Transparency

For off-plan buyers, institutional investors, and our global diaspora clientele, watching your real estate asset rise from the ground up provides unparalleled peace of mind. Every month, our project management and engineering directorates log exact progress metrics, structural achievements, and high-resolution photographic logs directly to this public portal.

Active Project Progress Dashboards

1. Bahari Starlet (Kileleshwa)

Superstructure Frame & Elevation Works • Target: March 2027

0%

2. Bahari Central (Kilimani)

Substructure, Foundation & Basement Excavation • Target: August 2028

0%

3. Bahari Homes (Kilimani)

Project Handover & Sectional Title Deed Issuance • Completed

100%

Detailed Project Milestone Logs

🏗️ Bahari Starlet (Kileleshwa)

Target Handover: March 2027

  • Substructure & Foundation: Completed (100%)
  • Basement Parking Levels: Completed (100%)
  • Superstructure Framework (Floors 1–18): In progress / Level 12 active frame casting (65%)
  • Masonry & Partition Walling: Commenced on lower residential floors (35%)
  • MEP Rough-Ins: Scheduled for upcoming phase initiation.

Lead Engineer’s Field Note:

“Superstructure works on the 18-storey tower are advancing smoothly and safely. Structural framing has successfully reached the 12th floor. We are maintaining our strict structural integrity standards, curing protocols, and material load-testing, keeping the project fully on track for our March 2027 handover target.”

🏗️ Bahari Central (Kilimani)

Target Handover: August 2028

  • Site Clearance & Geotechnical Surveys: Completed (100%)
  • Excavation & Foundation Shoring: Completed (100%)
  • Substructure & Basement Parking: Active casting of deep foundation footings and heavy retaining walls (85%)
  • Ground Level Transition: Formwork preparation ongoing for the main podium slab pouring.

Lead Engineer’s Field Note:

“Excavation and foundation work for Bahari Central along Menelik Road has progressed exceptionally well. Heavy foundation slab reinforcement is currently underway. We are laying a rock-solid, over-engineered structural base to support the vertical ascent over our 24-month build cycle leading to August 2028.”

🏢 Bahari Homes (Kilimani)

Status: Fully Completed & Occupied

Handover Status: 100% Complete. All luxury residential units, high-speed elevators, and common amenities—including the indoor heated pool, the 1,000 SQM courtyard, fitness gym, and backup generators—are fully operational and under professional management. Sectional Title Deeds have been successfully processed at the Lands Registry and issued to respective unit owners.

The 4-Stage Construction Lifecycle

1. Substructure & Foundation

Comprehensive geotechnical soil testing, deep site excavation, perimeter retaining wall reinforcement, and basement slab pouring. This ensures a flawless, load-bearing base.

2. Superstructure Framework

The vertical ascent. Pouring primary reinforced concrete columns, suspended floor slabs, and framing the building’s exterior architectural silhouette.

3. MEP & Interior Fit-Outs

Mechanical, Electrical, and Plumbing. Installing high-speed elevator shafts, concealed wiring, water reticulation, plastering, premium tiling, and custom cabinetry.

4. Final Inspection & Handover

Rigorous quality assurance audits, live utility load-testing, Sectional Title Deed registration, and the official delivery of unit keys to our buyers.